Auditor: the city couldn't back 36 of 60 National Western Center bond expenses, and no one can show the campus is meeting its goals
The Nov. 19 audit makes 28 recommendations. The city and the campus authority agreed to 27; the Mayor's Office of the National Western Center rejected the one on invoice review. A design contract for the Livestock Center gets another year Dec. 2.
Denver Auditor Timothy O'Brien's office says the city and the National Western Center Authority haven't followed all the rules of the 2017 agreement that set up the campus, can't show it is meeting its tourism and money goals, and can't document every bond-funded expense. The audit is dated Nov. 19 (summary page, press release).
Why it matters: Denver voters approved $778 million in bonds for the campus and the Colorado Convention Center through Measure 2C in 2015. The audit says the Mayor's Office of the National Western Center reported $756 million in actual 2C bond spending on campus projects as of December 2025, and that a June 2025 agreement the City Council approved, worth an additional $800 million, brought the city's total project cost to $1.5 billion. That newer agreement wasn't part of the review.
What the auditors found
- Bond expenses. Auditors reviewed 60 expenses paid with 2C bond money from 2023 through 2025. The city didn't have enough evidence to support 36 of them, and there was no evidence anyone reviewed 18. Only three of the 60 had no problems.
- Construction invoices. Twenty-five of the 60 invoices were for construction and added up to about $140 million of the $143 million reviewed. The city's financial system held "only high-level summaries of billed costs," the report says.
- Unexplained lines. Two invoices each listed more than $488,000 for "program expenses" that the attached progress reports didn't explain. The office didn't answer auditors' questions about them. Three art installation invoices totaling $340,000 showed no sign of review.
- Reports the Council never got. The framework agreement requires the authority to send its audited financial statements to the mayor, the City Council and the auditor by April 1 each year. The 2023, 2024 and 2025 statements went only to the city's chief financial officer, and the 2024 one was two days late.
- No performance audit in nine years. The agreement requires a third-party performance audit at regular intervals. None has been done since it took effect Sept. 28, 2017. The authority says it plans one starting in 2027.
- Board conflicts. The authority couldn't produce conflict-of-interest forms for 2023 through 2025. Auditors found four directors serving between January 2023 and June 2026 with potential conflicts, and two community directors have been paid $250 monthly stipends since April 2023, still as of July 2026, although the bylaws don't allow pay for board service.
- Goals. The authority hasn't set measurable goals, and expenses exceeded operating revenue every year from 2019 through 2025. Only 60 of 149 events from 2023 through 2025 had any attendance estimate.
The one recommendation the city rejected
The Mayor's Office of the National Western Center disagreed with Recommendation 3.1, which asks for written procedures on what documents back up an invoice, where they're kept and how review is recorded. Its response says staff follow city fiscal rules and existing review processes (agency responses).
O'Brien's addendum says the office answered "N/A" when asked how several kinds of expenses were reviewed, and that the transportation department's review procedures, dated August 2020, cover construction invoices but "do not apply to more than half the invoices we reviewed." The auditor's September follow-up of a 2025 Livestock Center design audit, where the office had rejected seven of nine recommendations, found a similar recommendation only partly carried out.
"I am disappointed," O'Brien wrote in his letter to the city.
The other 27 recommendations were accepted, with deadlines running to June 30, 2028.
On the Council's agenda
On Wednesday, Dec. 2, the South Platte River Committee has a consent item extending the city's Livestock Center design contract with Populous by a year, to Dec. 31, 2027, with no added money (26-1804, meeting). The contract stays at $13,725,655.53. The request form says construction was substantially complete Dec. 1, 2025, and the extra time is for record drawings and LEED certification (request form).
The audit lands as the office changes hands. The city said executive director Michael Bouchard's last day would be Nov. 25, with Adam Paul, the mayor's government affairs director, as interim (our story). In the auditor's release, O'Brien said the report gives new leadership "an immediate checklist of things to do sooner than later."