National Western CenterDistrict 9
National Western Center's director is leaving as the city pulls $1.5 million from the campus maintenance account
Michael Bouchard, who ran the $1.6 billion campus redevelopment office since 2023, leaves Nov. 25. Adam Paul, the mayor's government affairs director, will lead it in the interim. A Long Bill companion on Monday rescinds unspent campus maintenance money.
Michael Bouchard, executive director of Denver's Office of the National Western Center, is leaving the city Nov. 25, and Mayor Mike Johnston has named Adam Paul, his director of government affairs, as interim director, the city announced Thursday, Nov. 12. Bouchard becomes town manager of Mountain Village on Jan. 1.
Why it matters: the office oversees what the city calls a $1.6 billion redevelopment of the National Western campus in District 9, next to the Globeville and Elyria-Swansea neighborhoods. The next phases, an equestrian center and plans for the land known as the Triangle, are still ahead.
The change
According to the release:
- Bouchard led the office since March 2023 and had worked with Denver Parks and Recreation and the National Western office since February 2013.
- Paul, a former Lakewood mayor, keeps his government affairs job while leading the campus work.
- A permanent director will be hired through a search, with "updates to follow."
Johnston praised Bouchard's "steadfast and unwavering leadership." Paul said he looks forward to building on "the tremendous work already underway at the National Western Center."
The announcement came two days after the city said deputy chief operating officer Dominick Moreno is leaving for the state budget office (our story).
Where the campus stands
Bouchard briefed Council members at Mayor-Council on Aug. 25 (video). From that presentation:
- The livestock center opened in January and replaces the old Hall of Education (video).
- An equestrian center is next, with a development agreement being finalized; it replaces the old events center and frees up the Triangle (video).
- The Triangle is in community planning, with the plan to wrap up in 2027 before moving to implementation. Bouchard said the city was looking at community ownership and affordable housing there (video).
The campus's main partners are the National Western Center Authority, the National Western Stock Show and CSU Spur, he said.
What our records add
$1.5 million comes back from the campus account. The capital rescissions bill on Monday's agenda, 26-1641, takes back $1,500,000 from "National Western Center (NWC) Capital Maintenance," one of the five largest lines in the $16.1 million package (list, our story). The Finance Department says rescinded money comes from completed or deferred projects and is reprogrammed in the next year's budget; it doesn't explain this line.
The Council's campus votes this year:
- Jan. 5: two reappointments to the National Western Center Authority board (25-2092, 25-2093).
- Feb. 9: a construction contract with Ames Construction for a pedestrian bridge on the campus (26-0071).
- April 6: a fourth amendment to Merrick & Company's design contract to finish the campus's "horizontal infrastructure" (26-0235).
What's next
- Monday, Nov. 16: first reading of the rescissions bill, with the Long Bill (meeting).
- Nov. 23: final votes on the Long Bill and its companions.
- Nov. 25: Bouchard's last day.