Community Planning and Housing

Tuesday, August 18, 2026, 1:30 p.m. (Denver time), City & County Building, Room 391

Video of the meeting

On the agenda

Documents

Summary

The Community Planning and Housing Committee received an update on the City's data center regulation process, including the status of the one-year moratorium on new data center development (signed May 21), the selection of an outside facilitation team, and the launch of an open public application process for a data center working group (applications opening August 21, due September 4, first meeting planned for October 9). Sponsors acknowledged the moratorium will likely need to be extended beyond May 2027. Members asked about working group composition, budget (just over $400,000 from the Climate Protection Fund), engagement in environmentally burdened neighborhoods, and treatment of the data center currently under construction (which is not affected by the moratorium but would face new rules for future buildings). The committee also heard a rezoning action item for two parcels at 3418 West 14th Avenue and 1371 North Julian Street (church property in West Colfax), recommended for approval by CPD staff, with questions about height incentives, protected-district standards, and neighborhood outreach; a motion carried it through committee toward a public hearing.

Transcript

0:06 Welcome back to this weekly

0:07 meeting of the community

0:08 Planning and Housing Committee

0:10 with Denver City Council.

0:14 Your Community Planning and

0:17 Housing Committee starts now.

0:27 The afternoon, everybody who

0:31 coming to community planning

0:35 housing. You cut me meeting

0:38 today AUGUST 18th and I'm

0:40 COUNCILMAN Man have the honor

0:43 of chairing we have great

0:48 agenda We something that my

0:49 colleagues have asked for this

0:51 to come before us and then one

0:55 action item time her. For

0:57 that, we'll get started from

0:58 scratch there. Introductions

1:01 affect Good afternoon. Answer

1:01 to survive. Good afternoon,

1:04 Campbell, Southeastern

1:05 purchased reports. It happened

1:07 under a Watson Fine District.

1:12 9 and afternoon, Paula Pashman

1:13 Soft and British troops credit

1:14 to be just like district Jamie

1:20 Torres was 3 great. So we have

1:20 update to the data center

1:22 breaking count think you comes

1:26 Write hey, everybody said

1:27 Gonzalez could get as council

1:31 member at large Thank Surely

1:34 have great agenda. Pass it

1:37 over to my colleague Good

1:38 afternoon. Thank you,

1:39 colleagues. Thank Committee

1:40 chair Cent of for critics

1:44 based on today's agenda for

1:45 briefing on data centers

1:47 provide the update on data

1:47 centers as we the status of

1:49 the creation of the working

1:51 group. Our plan, community

1:53 engagement process. And then

1:55 our next steps and we look

1:57 forward answering questions

1:58 from you and providing to the

2:01 community here in the room as

2:02 well as community members on

2:03 viewing online. Some

2:05 background information that is

2:06 absolutely necessary. And

2:07 we're looking forward to doing

2:09 that. I want to start first by

2:10 thanking City Department's

2:11 supporting this process

2:13 throughout the mayor's office,

2:14 especially Victoria, who's not

2:16 here and I hope you're feeling

2:18 better for facilitating a

2:20 planning process. Apartment

2:23 leads and the mayor's office

2:24 are here and available data

2:25 the co chairs are console

2:28 co-sponsors of this would

2:28 answer questions. I want to

2:29 thank the community members

2:33 that are here and the chambers

2:36 as well as those online and

2:36 those who have been providing

2:39 continued feedback throughout.

2:42 I want to turn this over to

2:44 pro. Tem can for some comments

2:44 and then to counter Cashman to

2:49 kick off the presentation.

2:49 Thank you so much,

2:50 Councilmember Watson. I do

2:53 want to thank both you and

2:54 COUNCILMAN Cashman the

2:55 partnership and work that we

2:58 have been doing leading up to

3:00 this update. I'm grateful how

3:04 far we have gotten so far and

3:05 the fact that we're going to

3:05 provide, I think these very

3:06 important updates for the

3:09 public and for our colleagues.

3:10 So they kind of know what's

3:13 coming up next. And the last

3:14 thing I'll just say to preface

3:16 the presentation today is that

3:20 we realize that although it's

3:23 a a one-year moratorium, you

3:24 know, we are prepared and we

3:25 know and COUNCILMAN Cashman

3:28 said this from the beginning

3:30 is that if it it's going to

3:31 take as long as it needs to

3:32 take and because we want to do

3:33 the work and want to do it the

3:35 right way. And so I really

3:36 value everyone that has been

3:39 part of this process. And

3:40 thank you to COUNCILMAN Watson

3:43 and COUNCILMAN Cashman for

3:46 doing that lifting today and

3:46 and presenting since I am

3:47 virtual. It just will bake

3:49 more sense for them too. Walk

3:50 through the slides with

3:51 everybody, but I will be here

3:53 and will be available for

3:54 questions as well and to

3:55 assist my colleagues. Thank

3:58 you so much. Thank you,

4:02 COUNCILMAN. Those contends.

4:07 Next slide, As you can see, we

4:11 50 data centers in Denver from

4:14 the smaller size clay. Large 5

4:17 of the used entirely status

4:23 honors and others are

4:29 secondary We next line, ok,

4:30 and need pay attention at You

4:34 become that data centers in

4:35 Denver have no regulation and

4:39 data centers anywhere have a

4:43 large community impact the

4:46 enormous electricity use that

4:49 data centers can consume

4:51 enormous water used a variety

4:52 of other health pollution

4:55 concerns, noise and so on as

4:59 well as basic everyday zoning,

5:00 you know, is is always say

5:02 there's we build 20 story.

5:04 Buildings are larger downtown,

5:07 but we don't build them

5:08 everywhere. There MAY be a

5:10 spot for data centers, but

5:11 it's not going to be

5:12 everywhere. So we need to pay

5:16 attention to that. And this

5:17 body voted through a

5:20 moratorium and middle of MAY

5:21 MAY 18th and council goes. I

5:23 chair has pointed out. It's a

5:27 one-year moratorium. But as

5:28 the court meeting committee

5:30 that's been working to put

5:31 together. The working group

5:34 has decided it's starting to

5:35 look like the proposed cadence

5:36 of meetings. He's not going to

5:40 get done within that one year.

5:42 So it's increasingly likely at

5:43 some point will be coming to

5:47 the full body to recommend

5:50 continuation the moratorium

5:54 and not moratorium was signed

5:58 on. MAY 21st. So as of MAY,

6:02 2027 until that date, at least

6:05 on new data center development

6:09 and construction is If there

6:13 are plans process that has

6:14 been permanently, they will be

6:18 allowed to proceed. Slide,

6:28 please. Some the coordinating

6:33 led Kiser director Liz Babcock

6:39 hired a facilitation group.

6:40 Couple organizations, group of

6:41 14 engineering and civic

6:44 consulting collaborative

6:46 together. They will lead the

6:50 working group process and they

6:52 I believe online. I'm not sure

6:54 if we have anyone in the

6:56 audience audience from

6:57 consultants, but they're

7:00 available to answer questions.

7:01 Council Watson much take it

7:03 from Thank you so much.

7:04 Councilmember Cashman on the

7:05 working group to provide a

7:07 little bit of background we

7:08 share that sent the last

7:08 committee meeting. But we

7:09 wanted to make sure we

7:11 repeated during this meeting

7:12 and a working group will

7:16 include the 3 council sponsors

7:17 of them are Torrance. And as

7:20 councilmember Cashman Pro Tem,

7:24 Gonzaga tears folks from the

7:26 Utilities, Xcel Energy Union

7:28 members, industry wraps

7:29 advocacy groups and community

7:30 members as well as subject

7:33 matter experts and what we're

7:35 to find a subject matter.

7:36 Experts with city staff

7:38 playing a supporting role. We

7:40 want to also be very clear as

7:41 the city council member that

7:43 represents district 9 and the

7:46 center that's being built

7:48 currently in the city is and

7:49 go pillars want we are going

7:52 to focus to ensure that

7:54 community participation on

7:56 board reflects the geographic

7:57 impacts on gs as far as the

7:58 number of folks from that are

8:00 going to be committee members

8:04 on that working group, not the

8:07 board council mayor's office

8:08 and city staff will initially

8:09 recommends specific working

8:12 group members and that

8:14 recommendation has been made

8:15 already. Then also what we're

8:19 going to do is send out an

8:20 application to community

8:22 community members can apply,

8:22 including initial folks that

8:25 were all identified through

8:27 first step process that began

8:29 in MAY. So community members

8:30 will be able to have an

8:32 opportunity to apply to be a

8:36 part of this working It's our

8:37 expectation to have a clear

8:39 list who the members of this

8:41 working group in by OCTOBER to

8:44 the latest we'll have more

8:45 specifics and once again be

8:46 consultants that we hired and

8:47 we wanted to make sure we had

8:51 a consulting group, someone

8:53 outside of the city, someone

8:56 outside of the mayor's office

8:58 outside of City Council.

8:59 Actually going through leading

9:00 of facilitating that

9:01 application process. We

9:02 thought that was important.

9:03 They have a criteria for how

9:06 their son we will be selecting

9:07 and its election group. That's

9:10 going to be doing that. But we

9:12 look forward to Our focus is

9:13 to ensure an equitable

9:14 process. And so the open

9:17 public call for applications

9:17 on will begin to to provoke,

9:18 to serve. And a data center

9:20 working group and will launch

9:24 this AUGUST. 21st. So more

9:26 information will be provided

9:27 on that announcement found out

9:28 today. Applications will be

9:32 doing by SEPTEMBER 4. That is

9:33 awesome. So the application

9:34 will be by SEPTEMBER 4th with

9:38 expectation that we will have

9:38 clear list of working group

9:39 members within next several

9:45 Thank you, sir. And the

9:45 weeks after that. Next slide.

9:46 working group will focus some

9:49 of these topics as high level.

9:50 Obviously there other impacts

9:51 from data centers on that.

9:53 We're going to look at based

9:55 on the folks on the working

9:55 group. But at a very high

9:57 level, we're going to look at

9:58 obviously public health

10:01 impacts direct impacts,

10:01 community, health community

10:05 whether it's physical,

10:06 geography, location,

10:06 proximity, climate goals. We

10:08 have an amazing team of folks

10:09 here with city and county of

10:10 Denver has been providing us

10:12 direction on this thus far and

10:14 it will continue to provide us

10:17 direction, fair utility costs.

10:18 We're going to continue

10:20 working with on excel on on

10:21 utility to ensure that this

10:24 process looking at impacts to

10:25 communities and their data

10:26 centers that they're not

10:28 adversely impacted by utility

10:29 costs are changes, technology

10:31 needs. So we'll have folks on

10:34 the working group can speak

10:35 technology needs and then

10:36 additional development

10:39 question. So we expect to have

10:41 a wide range of individuals

10:43 from lived. Experience to

10:43 professional experience on

10:46 this working group providing

10:47 direct feedback to the team

10:49 with the expectation that we

10:52 will help build regulation

10:52 over that 12 month process on

10:54 that we have for that 12 month

10:57 moratorium. The working group

10:58 will pay special attention to

11:00 vulnerable communities and

11:01 adversely impacted community.

11:02 So we're gonna have an equity

11:03 lens as we identify the folks

11:09 that are working group and

11:10 lens throughout this process.

11:12 The goal is to review and

11:14 process proposed updates,

11:16 Denver's zoning and municipal

11:18 codes, building an energy

11:18 Sanders and other city

11:20 policies. So there is material

11:22 outcome of this working group.

11:23 As we celebrate those voices,

11:26 we want to make sure at the

11:27 end we have a regulatory

11:28 environment within city county

11:29 of Denver to regulate when

11:31 where and how data centers can

11:34 be Public participation all

11:35 share this a high level. Once

11:36 again, believe the consultants

11:39 or online at they're not. We

11:40 have members from the city

11:43 that can speak just to deeper

11:43 in today's criteria. But the

11:44 city is launching several ways

11:45 for community members to get

11:46 involved and make their voices

11:47 heard throughout the process.

11:48 The open call, as we just

11:51 described as being sent out by

11:53 the end of this month about

11:54 public participation at

11:55 virtual and in-person meetings

11:59 and there will be in town

12:00 halls job committee members to

12:01 attend throughout as They'll

12:03 be a website dedicated to

12:05 best. They'll be on

12:06 communication and everything

12:08 will be with language access,

12:10 so be in English and Spanish,

12:11 primarily and obviously with

12:11 throughout the city, we have

12:14 the ability to translate the

12:15 language what have designated

12:16 email to capture community

12:19 feedback. So folks communicate

12:20 directly back to an email if

12:21 they're not able to

12:22 participate in-person or

12:23 virtual that some of those

12:26 touch points. As I stated

12:27 language, justice

12:28 interpretation can sure all

12:31 voices are and it will publish

12:32 a draft policy recommendations

12:34 for public comment. Obviously

12:35 the regulatory process will go

12:36 to regular city council

12:38 process, which means we'll

12:40 come back. The city at the end

12:42 of this process and throughout

12:46 to make sure we have the full

12:49 vetting of the possible go

12:50 through the City Council

12:52 Whenever that process through

12:56 the end of MAY more longer, if

12:58 we have to prolong spot the

12:59 process. We are not trying

13:03 finish by a certain date time.

13:04 We have 12 month moratorium

13:06 but we will go on till we are

13:08 completed until we have a

13:09 regulatory architecture that

13:10 we think is ready for the

13:12 Florida ready for City Council

13:14 to debate high levels.

13:16 Timeline we had initial

13:17 discussion about data centers

13:20 back in OCTOBER 2024. In it,

13:21 Johnson wrecked center and I

13:23 won't go each of these, but we

13:24 wanted to put a few of the

13:26 touch points that we've had

13:28 thus far within process. And

13:31 then we are here today

13:32 presenting before this

13:34 committee with the hope and

13:35 expectation to begin the

13:38 process. A call for working

13:38 group members going up at the

13:42 end of this month. Immediate

13:43 next steps we're going to

13:44 Denver. Gov dot Org. Data

13:46 centers, backslash data

13:49 centers. That will be a

13:50 website that will hold all of

13:53 the information. All the input

13:54 all around data center. Folks

13:55 have a one-stop shop to look

13:59 and check on around. Data

14:00 centers were going shoot the

14:02 open call for public

14:05 applications or begin

14:05 collecting community feedback

14:08 and questions. And we're ready

14:09 collecting information right

14:09 now. So folks are provided

14:11 feedback on data centers. That

14:12 information is going to be

14:13 continued collecting. And

14:14 that's by the end of AUGUST by

14:18 the end of OCTOBER, will

14:18 select finalize announce a

14:19 working group members host a

14:20 public meeting with working

14:22 group members and launch more

14:25 resources and ways for public

14:26 participation. Lots of

14:27 information and I appreciate

14:29 everyone's attention. Turned

14:31 over to co-sponsors. See,

14:32 there's any last thoughts then

14:35 open up for any questions that

14:38 folks Thank you. I let me pass

14:41 it on the of scooter as first.

14:42 See if pro time. Do you have