Denver's tree protection rewrite returns to committee after two months, minus its arborist requirement
The bill would protect more private trees during construction, create 'legacy trees' and charge builders who can't plant required street trees. Parks staff dropped a rule that could have made developers hire an arborist.
A rewrite of Denver's tree rules comes back to the Council's Parks, Art and Culture Committee on Tuesday, Dec. 1, nearly two months after the committee postponed it (26-1451, meeting). On Oct. 6, Flor Alvidrez moved to postpone it to a date certain, Chris Hinds seconded, and the motion carried, the record shows.
Why it matters: the bill sets when a builder can cut down a tree, what it owes when it does and which trees are off-limits. It would take effect April 1, 2027.
What the bill does
The parks department's slides list eight changes to Chapter 57 of the city code (slides), and the Nov. 19 draft spells them out (draft):
- More private trees protected during construction. Removing an established tree in a "protected setback" during demolition or construction would need a permit from the city forester. The draft defines that as the front or street-side setback of a zone lot under the old zoning code, or the primary or side-street setback of a zone lot under the current Denver Zoning Code. The slides call this "expanded protection for private trees in street setbacks." An established tree is one with a trunk at least 4 inches across, measured 4.5 feet up.
- Legacy trees. A new program to designate exceptional trees: 18 inches or more across, more than 50 years old, a unique species or with historical or cultural significance, among other criteria. Once designated, the owner can't remove, damage or fail to maintain it. The designation is recorded in property records. The owner, the city forester, the parks director or a Council member can apply; anyone else needs the owner's signed consent.
- Payment in lieu. A builder required to plant street trees who can't, because of site conditions, would pay per tree into the Public Tree Canopy fund before getting a building permit. The rate follows the market; the slides put it at $1,600 and say it won't change for now.
- Also: new definitions, a consistent appeals process and updated licensing for tree contractors.
What changed since October
The proposal the committee saw in October included a rule letting the city forester require a builder to hire a certified consulting arborist to monitor a protected tree during construction. The new slides say: "Delete recommended language from proposed changes at this time," adding that similar language may come back later. The Nov. 19 draft doesn't include it.
What's not in the bill
The slides also answer feedback the department calls "outside of project scope," with price tags for ideas it's discussing but isn't proposing in this bill:
- Expanding hazard removal and pruning of street trees beyond equity neighborhoods: about $500,000 a year.
- Contractor help for storm response: about $150,000 a year.
- Structural pruning of more street trees: $9 million to $16 million a year.
- Two years of watering for newly planted city trees: about $500,000 a year.
On tree of heaven, an invasive species, the slides list options including requiring removal during development review, with no change proposed now. On sidewalk repairs, they cite an executive order on tree removal mitigation and an agreement with the transportation department that's still being written.
The slides count 6,460 outreach "touchpoints," including two surveys with 4,800 responses.
What's next
- Tuesday, Dec. 1, 10:30 a.m.: committee (meeting).
- Dec. 8: Mayor-Council. Dec. 14: first reading. Dec. 21: final vote.
- April 1, 2027: effective date, according to the slides.