InfrastructureCommittee results
Denver bond changes clear committee: an Army Corps review sank the Kennedy soccer restroom
The Transportation and Infrastructure Committee voted 4-0 after waiting for a fourth member. Staff said Yale Avenue work centered on Holly Street.
Changes to the project lists for Denver's 2017 Elevate Denver and 2021 RISE Denver bonds cleared the Council's Transportation and Infrastructure Committee 4-0 on Wednesday, Nov. 18, after the committee waited most of the meeting for enough members to vote (26-1729, 26-1730, roll call).
A third item extending AtkinsRealis's contract to manage both bond programs through 2029, with no added money, passed the same way (26-1731).
Why it matters: the lists are how voter-approved bonds become specific parks, libraries and street projects. Our earlier story noted the city's written requests didn't say why a restroom at the Kennedy Soccer Complex was being dropped. Staff explained it Wednesday.
Why the Kennedy restroom came off
The restroom ran into "a number of regulatory issues," most of all with the U.S. Army Corps of Engineers, a bond program manager told the committee. Because the Corps manages that land, the city would have had to federalize the project and go through a full federal environmental review, the manager said, taking longer than the bond allowed (video).
Instead, the manager said, the restroom will be built as part of the Vibrant Denver bond's Southeast Recreation Center and Skate Park project, which can share plumbing. In the meantime, RISE money goes to replacing basketball courts across District 4, which Council President Diana Romero Campbell represents (video). The slides list two added court replacement projects in District 4.
Yale Avenue: from a corridor to an intersection
The bill drops "I-25 to Quebec" from the "Yale Avenue Improvements" project name. Staff said the bond language promised to assess and make safety improvements along the corridor, and the assessment found the main problem was the Yale and Holly intersection, which became the major project. They said the city also did accessibility work on other sidewalks and intersections (video).
A council member noted the segment is about 2 miles and asked what the original budget was. The manager said the dollar amount wasn't at hand and promised to follow up (video).
No more votes for renames
The bills also say a future name-only change to a listed project won't need another ordinance, matching the language in the Vibrant Denver bond, the slides say. The other renames: Fox Run Park (District 11), Bethesda Park (District 4) and the Ross-Phyllis Bigpond Branch Library (District 3).
Advertisement
Where the programs stand
The slides say the two programs are delivering 569 projects, 83% are complete and 474 have opened to the public, 425 from Elevate and 49 from RISE. The city expects to substantially finish both by the end of 2027, with administrative closeout through 2029. That's the reason for the AtkinsRealis extension, the manager said: work continues after the ribbon-cutting (video).
The vote
Flor Alvidrez, the chair, Kevin Flynn, Chris Hinds and Shontel Lewis voted yes. Stacie Gilmore, Amanda Sandoval and Romero Campbell were absent, according to the roll call.
Early in the meeting the chair said the committee didn't have a quorum and set the items aside. The vote came near the end, after the Waymo briefing (video).
What's next
The bills go to Mayor-Council and then two Council readings. The contract extension, a resolution, needs one Council vote.