Is there money for construction-hit businesses in 2027? What the budget bills show
A Gazette report says the BIO Fund has nothing for next year. The mayor said in October he'd make up to $2 million available, and a bill on Monday's agenda adds $400,000 in federal relief interest. The budget doesn't break out a BIO line.
The Denver Gazette reported Saturday that the city's grant program for small businesses hurt by city construction "has no funding for 2027," and that with the budget already set, it's unclear where money for a permanent version would come from (Gazette).
The city's records point to at least some money for next year. Here's what they show and what they don't.
Why it matters: the Business Impact Opportunity Fund, or BIO Fund, gives one-time grants of $7,500 or $15,000 to small businesses that can show construction cut their revenue. A bill to make it permanent cleared committee Nov. 10 and is on Tuesday's Mayor-Council agenda (our story). If it passes, businesses near the next long street projects would be in line for help without a yearly budget fight.
What the records show
Up to $2 million, promised in October. Responding to the Council's budget requests, Mayor Mike Johnston agreed to make up to $2 million available for the program, Colorado Politics reported Oct. 19. The Council had asked for $4 million.
"Increased support," no figure. The mayor's Nov. 6 letter accepting the Council's amendments lists "increased support for Denver businesses impacted by construction" among Council-driven changes in the final budget, without a dollar amount (letter).
$400,000 on Monday's agenda. One of the Long Bill's companion bills, 26-1649, would put $400,000 in interest earned on Denver's federal pandemic-relief money toward the BIO Fund in 2027. The Finance Department calls it "part of the Mayor's response to the City Council 2027 budget letter" (request, our earlier story). It's up for first reading Monday, Nov. 16 (meeting), with a final vote expected Nov. 23.
No BIO line in the Long Bill. The 2027 Long Bill, 26-1638, appropriates General Fund money by agency, not program. It gives Denver Economic Development and Opportunity, which runs the BIO Fund, $4,669,665 in the General Fund, but the bill doesn't say how much of that is for grants. So the budget documents we've reviewed don't settle how much grant money there will be next year beyond the $400,000.
Where the permanent program would get money
The ordinance, 26-1712, would require the city to set aside at least 1% of the cost of city construction projects between $10 million and $25 million that last a year or more, and 1% to 5% of projects over $25 million that last at least 18 months. The money would come from the General Fund, not the capital budget, and a companion bill, 26-1719, creates a fund that keeps unspent money and interest from year to year.
Advertisement
At the Nov. 10 committee meeting, co-sponsor Amanda Sawyer said, "The funding source for these dollars is the general fund," and that because each qualifying project must set aside money, "it has to be funded" (video).
Adeeb Khan, executive director of Denver Economic Development and Opportunity, told the committee the program has made more than 3,000 grants over its life (video). It began in 2019 as a pilot for businesses near Interstate 70 construction, and it helped 100 businesses in 2025 and 88 so far this year, the Gazette reported. The paper quoted Khan saying the program "will not make businesses whole."
What our records add
Who is sponsoring it: Flor Alvidrez, Chris Hinds and Amanda Sawyer. The committee vote was 6-0, with Stacie Gilmore absent (roll call).
Timing. The sponsors want it adopted this year so it starts Jan. 1, 2027. The Council adopted the 2027 budget Nov. 9, before the ordinance reaches a final vote. The records we reviewed don't say how the set-aside would apply to projects already in next year's budget.