A resolution approving a proposed Contract between the City and County of Denver and Flatiron Dragados Constructors, Inc. for CM/GC Construction Services for the Morrison Road Improvement project between Sheridan Blvd. and Stuart Street, in Council District 3. Approves a contract with Flatiron Dragados Constructors, Inc. for $12,138,066.51 with a term of NTP + 424 Days for CM/GC Construction Services for the Morrison Road Improvement project between Sheridan Blvd. and Stuart Street, in Council District 3 (DOTI-202684509). The last regularly scheduled Council meeting within the 30-day review period is on 7-20-2026. The Committee approved filing this item at its meeting on 6-17-2026.
26-0831 · Resolution · Adopted
Timeline
- Jun 17, 2026: approved by consent (Transportation and Infrastructure)
- Jun 29, 2026: adopted (City Council)
- Jun 29, 2026: signed (Council President)