A resolution approving a proposed Amendatory Agreement between the City and County of Denver and AMES CONSTRUCTION, INC. for the Buchtel and Colorado Improvements project construction services, in Council District 6. Amends a contract with AMES CONSTRUCTION, INC. to add $14,409,718.85 for a new total of $16,118,863.06 and to add 377 days for a new end date of 11-27-2027 for the Buchtel and Colorado Improvements project construction services, in Council District 6 (DOTI-202580459/DOTI-202683087-01). The last regularly scheduled Council meeting within the 30-day review period is on 6-8-2026. The Committee approved filing this item at its meeting on 5-6-2026.
26-0594 · Resolution · Adopted
Timeline
- May 6, 2026: approved by consent (Transportation and Infrastructure)
- May 18, 2026: adopted (City Council)
- May 18, 2026: signed (Council President)