A resolution approving a proposed Contract between the City and County of Denver and Iron Woman Construction & Environmental Services, LLC for the East 16th Avenue Storm Phase 2 project, in Council District 9. Approves a hard bid construction contract with Iron Woman Construction & Environmental Services, LLC for $20,352,466.50 and for NTP +365 Calendar Days for the East 16th Avenue Storm Phase 2 project, in Council District 9 (202475601). The last regularly scheduled Council meeting within the 30-day review period is on 3-24-2025. The Committee approved filing this item at its meeting on 2-18-2025.
25-0176 · Resolution · Adopted
Timeline
- Feb 18, 2025: approved by consent (Land Use, Transportation & Infrastructure Committee)
- Mar 3, 2025: adopted (City Council)
- Mar 4, 2025: signed (Council President)